Lyons Construction began pulling out the floating docks at the East Jordan city harbor during the week of October 20. Dredging comes next, and the city expects it to run until the weather shuts it down. A short walk up Main Street, the old Civic Center at 116 Main has been vacant since 2020. The most recent steps toward its demolition were a round of bids due in September and a brownfield meeting set for October 27.

The harbor is on a construction schedule that ice will interrupt, and the city has set June 2027 as the target for reopening. The Civic Center site is still working through grant administration, demolition bids and a brownfield plan, and its new building isn't expected to be ready until early 2028.

The harbor's schedule depends on the weather

The harbor work has been on the city's calendar since late summer. The East Jordan Downtown Development Authority's September 14 minutes set out the plan: close the harbor in mid-October, dredge in the fall and install new docks in the spring. Here is how the dates have lined up since then:

  1. Mid-October: the harbor closes for the season and for construction.
  2. October 6: the City Commission hears that Atlas Electric and Lyons Construction will start preliminary work, full demolition of the floating docks, and dredging later in the month.
  3. Week of October 20: dock demolition starts, then infrastructure work, then dredging.
  4. Spring 2027: the new docks go in.
  5. June 2027: the city's goal for opening the new facility, as stated in its State of the City 2026 report.

The City Administrator's October 20 report, included in the City Commission's October 20 agenda packet, states the limit on step three plainly:

"Upon demolition and infrastructure improvements, dredging will take place until winter sets in."

The plan doesn't fix an end date for dredging. Freeze-up does. Docks can't be installed on frozen water, so that work waits for spring. June 2027 is a target, and it depends on how long this fall stays open and how early next spring arrives.

The project covers more than new boards on the water. According to the October 6 bond resolution, it includes new floating docks, electrical upgrades, dredging, demolition and related site work. A $1 million state grant supports it. According to the October 6 meeting minutes, the commission approved Resolution 115-2026 that night, a notice of intent to issue up to $1.9 million in capital improvement bonds for the marina, to be repaid from what harbor users pay. The notice is to be published in the Charlevoix County News.

The contractors are local, too. Atlas Electric's office is at 6025 M-32 in East Jordan. In an October 1 email in the commission packet, the company offered a $28,000 deduction if the two electrical distribution panels moved to the fixed dock, which had come up at the preconstruction meeting. The October 20 agenda listed the marina change order as new business.

116 Main Street has more than a century of history

The old Civic Center site has turned over before. The 0.45-acre lot at 116 Main was first built on in 1901 as the Lake Side Hotel and Livery. It later served as a storage yard for the Charlevoix County Road Commission and then as a public community center. According to the city's 2020 Master Plan, the lower-level gym was open to the public year-round and hosted recreation groups, service organization events, blood drives and parties, while the East Jordan Senior Center used the upper floor. The senior center has since moved to the old elementary school.

Those decades of use also left soil problems. In 2025, site investigations paid for by the state found metals and organic compounds in the soil, likely from fill brought onto the lot over the years. In August, the Michigan Department of Environment, Great Lakes, and Energy awarded an $805,000 brownfield grant. It pays for more environmental assessment, demolition and asbestos removal for two buildings, and the hauling and disposal of about 4,500 tons of contaminated soil.

The project that comes after the cleanup is called Lakeview Lofts. The City Commission approved agreements with EJ Development Group, LLC in 2025, including an amendment on February 4 and amended purchase and development agreements on June 3. The plan described in the state's release is an $8.6 million, 22,800-square-foot building with commercial space and 17 homes, a mix of for-sale condos and rental apartments. Eight of the homes are reserved for households earning 60% to 120% of the area median income. The project is expected to create 12 jobs. 9&10 News covered the grant when it was announced on August 19.

Why the empty building is due back later

On paper, the Civic Center looks further along than the harbor. The agreements are signed and the grant has been awarded. But the cleanup has to finish before anything new can be built, and the cleanup depends on several steps that each wait for the one before.

The steps after the grant were already lined up in the summer. At the August 4 commission meeting, the City Administrator reported that with the award in hand, demolition bidding and the brownfield plan could begin, possibly with work starting in the fall. The DDA's September minutes said demolition bids were due in September and that the city was hoping to remove the buildings that fall. The October 20 report listed the next step as a brownfield meeting on October 27 at 5:30 p.m. to review the redevelopment plan, with consultants from EGLE and Fleis & Vandenbrink attending.

Each of those steps moves at the pace of meetings and filings. The harbor is already under construction, and the Civic Center is still in planning, which accounts for the gap between June 2027 and early 2028.

A third waterfront property is waiting on outside money. The September DDA minutes report that the development agreement for the old boat launch property is on hold because the state cut its funding.

Where downtown's season happens this year

With the harbor closed and 116 Main empty, this year's holiday calendar runs through City Hall, the American Legion Hall, The Depot and G.A.R. Park. The East Jordan Chamber of Commerce has posted three dates:

  • Thursday, November 19, 4 to 7 p.m.: Small Business Thursday Shopping Night, with discounts, open houses and a punch-card prize drawing at participating businesses.
  • Saturday, December 5, 11 a.m. to 1 p.m.: Santa and Mrs. Claus at City Hall, plus a soup cook-off at the American Legion Hall and a downtown Santa scavenger hunt that starts and ends at The Depot.
  • Sunday, December 6, 5 to 6 p.m.: tree lighting and community caroling at G.A.R. Park, followed by cocoa, cookies and crafts at the American Legion.

For a warm stop between events, Iron Goat Coffee at 101 Main St. lists hours of 6:30 a.m. to 4 p.m. on weekdays and 7 a.m. to 4 p.m. on weekends.

Both waterfront projects have been funded at a busy time for the town. The city's State of the City report says this fall's Fall Fest drew more than 2,100 people over Friday and Saturday, its best year so far. Tourist Park finished its season with 899 reservations and nearly 9,700 nights stayed across its campsites and cabins. When the new harbor opens, it will join a waterfront that already draws those numbers.

One more idea is still early. At the September DDA meeting, a board member reported on a meeting with Little Traverse Conservancy about a possible walking bridge over the Jordan River to connect with the Conservancy's Rogers Homestead Trail. The idea also includes non-motorized trails on the east side of the river leading into town and Community Park. For now it's at the investigation stage, without a funding source or a date.

We follow the harbor rebuild and the 116 Main cleanup closely because they shape the South Arm waterfront our clients care about. If you'd like to talk about what the new docks or the Lakeview Lofts plan could mean for a home near downtown East Jordan, The Crane Group is happy to walk through it with you. Schedule a Free Consultation.

Work with Johnny & Matt

Text to display: Johnny & Matt are two of Northern Michigan's most successful real estate agents and have helped hundreds of buyers and sellers achieve their real estate goals, resulting in over $100 Million of closed real estate transactions.

Follow Us on Instagram